News, insights, and case studies from Charlie Property — real stories, real numbers, and what we're learning as we go, exclusive for Money Partners.
Three old unit blocks on Jones Ave and Adelaide St, turned into 14 titles
.png)
.png)
Our two blocks on Jones Avenue, Moree
Quick one to properly explain this project, because "subdivision" is easy to skim past and it's the best bit of what we're doing in Moree.
We own three run-down unit blocks up there: two on Jones Ave and one on Adelaide St. Right now each one sits on a single title. We're subdividing all three under one strata process, and that turns 3 titles into 14. The two Jones Ave blocks go from 1 title to 3 each. Adelaide St, the big one, goes from 1 title to 8.
Why that matters for you: more titles means more ways to get money back out. Instead of selling one big property to one buyer, we end up with 14 separate units we can sell or rent one by one. That adds up to a lot more than the whole site sold in one line. It also spreads the risk. We're not hanging on one buyer, one valuation or one settlement to make the numbers work.
And the best news is where it's all at. The plans have gone into council, they've been well received, the trades are on site right now, and we're waiting on final approval. Once that lands we finish the renovation, get the occupancy certificates, the new titles get issued, and we pull the equity out as cash (x14). Below is the full rundown so you can see exactly who's doing what, roughly what it's costing, how long each stage takes and where it all goes from here, and why unit block subdivisions are the industry’s best kept secret!
.png)
Proposed New Floor Plan
This is the part worth reading twice.
Take the Adelaide St block. We picked it up for about $170K. One title, one tired building, eight units inside it. Once it's restored and retitled, it becomes 8 individual units that we expect to be worth around $200K to $210K each. That's roughly $1.6M to $1.7M of end value sitting inside a $170K purchase, before you count the build and consultant costs.
Then there's the rent. Each of those units is expected to let for around $250 a week. Across 8 units that's about $2,000 a week, or a bit over $100K a year in gross rent, out of one block that cost less than a single unit is worth on the other side.
The two Jones Ave blocks were bought for under $80K each and follow the same play at a smaller scale: 1 title becomes 3, each one its own saleable, rentable, refinanceable asset.
That's the whole model in one line. Buy the ugly block cheap, restore it, cut it into titles, and every title becomes its own little bank. When the titles land, equity gets pulled out as cash, and that cash is what pays back money partners and funds the next one.
All three are being strata subdivided. Each unit gets its own title plus a share of the common property, rather than a standard freehold land split. Regional NSW councils tend to move a bit easier on this than a Victorian council would, and that's working in our favour.
The council are also very keen in investment and restoration in the area and couldn't be better to deal with.
Figures below are rounded and approximate, pulled from invoices and correspondence on file — treat them as a good indication of scale rather than a final number.
Council Approval Group are handling town planning and council liaison — running the DA process end to end, from lodgement through council questions, and keeping every other consultant moving. That's been billed stage by stage as the work progresses, roughly $9,000 across invoices seen to date.
Zen Drafting Studio did the architectural drafting and DA drawing sets — full sets for all 3 sites, plus BASIX and NatHERS coordination. That's come to around $12,000.
Omega Project Services, a regional NSW firm, handled structural engineering and compliance — assessment and compliance reports across all 3 sites. About $16,000 in total: roughly $2,000 and $5,400 for the two Jones Ave blocks, and $8,600 for Adelaide St.
JSE Design put together the stormwater management plans and site layout drawings for all 3 sites. That's roughly $15,300 total — around $4,600 per Jones Ave block and $6,100 for Adelaide St.
SMK Consultants handled the land surveying — a detail survey of Adelaide St plus concept strata layout plans across all three sites. About $2,000 is confirmed on one invoice so far, with several more survey invoices still to be fully itemised.
Our own on-site trades have completed the remedial and structural works to date — about $15,000 paid just this week.
On top of that there's a bit of miscellaneous spend — a mixture of paperwork and general consulting — in additional amounts still coming through.
Council: Moree Plains Shire.
The DA for the first Jones Ave block went in first through the NSW Planning Portal, with the other two following the same path.
Council asked for three specific things on these sites: an asbestos report, a stormwater management plan and a building code compliance report. All three are done and lodged, which is exactly why the structural and stormwater consultants above were brought in.
The response from council has been positive, and we're now waiting on the final approval to come through.
Internal measurements across all 3 sites. First job. About a week.
Survey and concept strata layout plans (SMK). Roughly 5 to 6 weeks to get from raw survey to a workable layout.
Full DA drawing sets (Zen Drafting). The biggest single piece of work. About 10 weeks start to finish, including a round of revisions once council and the energy assessor came back with questions on window sizes, roof colours and yard layouts. All sorted.
BASIX and NatHERS energy certificates. Ran alongside the drafting. About 4 weeks all up, most of it waiting on final drawings rather than the assessment itself.
Structural engineering, quote to sign-off. About 3 weeks of comparing firms before we picked the right one at the right price.
Structural engineering, inspection to first report. Inspections on all three sites done in a day, first reports back within about a week. Roughly 3 to 4 weeks from sign-off to report in hand.
DA lodged. Went in as soon as the first drawing set was ready, with the other two following.
Stormwater management plans (JSE Design). Close to 8 weeks from quote to delivery. The longest single stretch, because regional consultants doing this kind of report are thin on the ground. Done and lodged now.
Remedial works on site. Underway now. Trades are on the tools while we wait on council, so the moment approval lands we're already moving.
.png)
What each unit would look like
The trades are on site and into it. Remedial and structural works are underway across the blocks, starting with the Jones Ave properties, so we're not sitting around waiting for a piece of paper. By the time final approval comes through, a big chunk of the groundwork is already done.
Jones Ave, block 2 is in great shape. The structural report came back clean, with minor wall gaps well within normal tolerance, fixed with a simple mesh and render method. Plans lodged, trades on site, waiting on council.
Jones Ave, block 1 is tracking right alongside it. Same drafting team, same process, now at 3 units instead of 2. Plans lodged, waiting on council.
Adelaide St has the most cosmetic building work ahead of it, but is the fastest to execute because the units are identical and so rinse and repeat!
Every stage before this one has been about paperwork, reports and approvals. Everything from here is about building, finishing and getting paid. The order of events is simple:
We'll keep the updates coming at each of those five steps, with photos, so you can watch it happen.
Regional consultants price higher, because there's less competition keeping them sharp. Every quote on this project, surveying, structural and stormwater alike, has landed above what a metro equivalent would cost. The fix has been simple: never sign on the first number. Getting a second quote every time has saved real money. The structural engineering alone would have cost close to double if we'd gone with the first quote that came in.
Running three properties as one project is paying off. Because all three sites go through council and every consultant together, we get project level pricing instead of three separate small jobs each carrying its own setup cost. That's a big part of why the combined structural bill came in well under the early per property estimates.
Three sites, three different stories. One Jones Ave block came back clean. Adelaide St needs more work. Good news on one site doesn't automatically mean good news on all three, and bad news on one doesn't drag the others down either. We'll keep reporting on each site on its own so you always know exactly where each of your dollars is sitting.
Using your own trades saves an incomparable amount. Its incomparable to the difference between sourcing local external trades, versus using our own in-house team. This is a learning we have had, as you know!
Cheap blocks, expensive titles. The single biggest lever in this whole model is the gap between what a tired unit block costs as one title and what it's worth as many. A $170K block becoming eight $200K units isn't a trick, it's just paperwork, patience and a good crew. That's the play we'll keep running.
Charlie only takes on a small number of money partners per deal, so it stays the right fit for both sides.
Become a Money Partner.png)
Charles Corby is the founder of Charlie Property. He built his career helping everyday investors grow wealth through smart property strategies, and now shares that experience through Charlie Property's education and investor communities.
Structured, transparent returns backed by real property. No surprises.